Zone: 1 Date: November 10th, 2024
Location/ Owner | Contractor | Start Date | Duration | Manpower | Schedule | Scope |
---|
Burns Harbor
PVS Steel Service | Hayes | Late Fall | 4 weeks | 8 per shift | 6-10s | Ductwork & Roaster |
Cliffs Burns Harbor
Sinter Plant | Morrison | December | 2 weeks | 25 per shift | 2 shifts 7-10s | Duct work, Fans, Windboxes, etc. |
Cliffs Burns Harbor #1 hood | Morrison | December 8th | 2 weeks | 15 per shift | 7-12s | Maintenance |
BP Whiting Refinery
| Nooter | early next year | TBD | TBD | \TBD | Spring: Dome replacement on tower, another Reactor
Fall: 600 Cat in fall Preoutage in July. Also aTar Outage Sept. |
Nipsco | BMWC | Spring | TBD | YBD | TBD | 2/3 week outage on unit #18
3/4 week outage on unit #12 |