Zone: 2 Date: NOVEMBER 6th , 2024
Location/ Owner | Contractor | Start Date | Duration | Manpower | Schedule | Scope |
---|
TATE & lYLE | KENNNEDY TANK | ONGOING | ONGOING | 11 | 5/10S | MAINTENANCE |
MEROM | STERLING | ONGOING | ONGOING | 1 | 5/8s | MAINTENANCE |
INGREDION | KENNEDY TANK | ONGOING | ONGOING | 10 | 5/10s | TANK BUILDING |
WABASH VALLEY RESOURCES | Freitag on the old unit and Sterling on the new work. | Summer of 2025 | 3-4 YEARS | TBD | TBD | FERTILIZER PLANT/HYDROGEN AND CARBON CAPTURE |
MAPLE CREEK ENERGY | TBD | 2025 | 1.5 YEARS | TBD | TBD | 660 MW GAS COMBINED CYCLE |
CAYUGA 650 MW new gas unit | GEMA, Kiewit, or Black and Veatch | BIDDING | 1.5 YEARS | 40 | Spring or so of 2025 | COMBINED CYCLE |
CAYUGA SPRING 2025 | STERLING | TBD | TBD | TBD | 6/10s | CATALYST and BOILER T&M |
Invenergy Sycamore Gas Plant | TBD | 2026 | 1-1.5 YEARS | TBD | TBD | GAS PEEKING UNITS 930 MW |
MEROM | STERLING an FREITAG | MAY 2025 | TBD | TBD | 6/10s | BOILER OUTAGE |
ELANCO | FREITAG | ONGOING | TBD | 2 | 5/8s | MAINTENANCE |